Selected work

The programs I’m proudest of, and how I ran them.

FLIGHT-SAFETY REDESIGN / PARKER MEGGITTFLIGHT-SAFETY REDESIGNDELIVERED

A flight-critical failure mode, traced back to our component after years of investigation. An 18-month redesign the customer needed in a fraction of the time. Delivered in six.

$1M
Direct cost each time a field failure pulled an engine off the wing
4mo
Critical design review turnaround, from a January kickoff
6mo
Of daily customer meetings, every workstream running in parallel
$4M+
In replacement costs avoided across the fleet
SCHEDULE COMPRESSION
18 mo plan 6 mo delivered
6 mo delivered18 mo original honest estimate
THE SITUATION

A field failure mode was traced back to our component after years of investigation. I led the root-cause work, including live teardowns with the customer on-site. Every confirmed failure meant an engine pulled off the wing for repair. That was real, direct cost, and very little patience from the operators flying those business jets.

THE ASK

Eighteen months was the honest estimate for the redesign. Due to the critical nature of the failure, the cost of repair, and the implications for the customer, it was imperative to deliver the program as efficiently as possible. The customer requested a critical design review four months from kickoff, and stayed engaged throughout the program to accelerate the review process, including an engineering manager who came on-site three to four times, more than his role would normally call for.

THE INVESTIGATION

I mapped the real critical path myself. The bottleneck wasn’t the engineering. It was long-lead test parts and review cycles that had been built in from a slower prior experience with this customer. Rather than absorb that quietly, I was transparent about where their own review cycles were adding time.

Transparency and a trusting relationship with the customer matter more to an efficient outcome than anything else. Building that rapport is what let us communicate honestly, keep the customer engaged, and cut wasted time out of the review cycles.

THE BET

I chose to qualify by similarity and analysis over new physical testing wherever it was defensible. That meant reconstructing evidence from sparse, disorganized legacy documentation, but it kept the schedule honest instead of padding it with tests we could justify avoiding.

RUNNING IT

Six months of daily customer meetings. Every workstream ran in parallel: testing, documentation, procurement, manufacturing. I was doing the engineering and the program management at the same time.

Much of the job was reading each person in the room, technical and non-technical, internal and customer-facing, and adjusting how I communicated so people felt included and bought into the approach and the overall outcome of the project.

THE OUTCOME

Delivered in six months. More than $4M in avoided replacement costs. Just as important, the customer relationship came out of a genuinely stressful program stronger and more trusting than it started.

Parker Meggitt · Technical Project Manager / Lead Technical Engineer · 10/2022–10/2025
HYPER-ELASTIC FOAM TEST BED / LOS ALAMOS NATIONAL LABORATORYHYPER-ELASTIC FOAM TEST BEDBUILT & TESTED

Another group at the lab needed a custom test bed and data acquisition system, with no standing team to build it. I assembled the effort from scratch and did it by building a cross-group partnership before any hardware was built.

Scratch
No standing team. Design, fabrication, instrumentation, and software all assembled from the ground up
Liaison
Single point of contact between the team executing the work and the requesting customer group
Built & run
First round of preliminary testing completed before grad school
THE ASK

Another group at the lab needed a custom test bed and data acquisition system built. No standing team existed for it. Design, fabrication, instrumentation, and software all had to be assembled from scratch.

THE GAP

Unlike Parker Meggitt’s more integrated team structure, this lab environment required actively pulling together expertise project-by-project: design engineering, manufacturing, procurement, instrumentation, and software, each living in a different group.

THE MOVE

I knew a software engineer in a different group and sensed that group could use the work as much as my team needed the expertise. I took the time to understand what that group actually needed before proposing anything, then brought forward a partnership that solved a real problem on both sides.

It worked because of the relationship and trust I had built with that group, not just because the skills happened to line up on paper.

RUNNING IT

I spec’ed and sourced the instrumentation, triaxial accelerometers, a force transducer, the vibration plate table, and the full data acquisition system. I coordinated the effort with the design engineering team. I acted as the main liaison to the requesting group, translating technical status into terms that kept a stakeholder group calm and informed. That covered status, risk, mitigation plans, schedule, and critical-path tracking.

THE OUTCOME

Built, assembled, and ran the first round of preliminary testing before transitioning to grad school.

Los Alamos National Laboratory · 04/2019–09/2020
COLLECTIONS / FULL-STACK APP
Screenshot of the Collections vinyl record collection app
BUILT SOLO

Built to solve a real problem: never knowing which vinyl records friends and family already owned or wanted for gifts. Built solo in Next.js, React, and TypeScript, under the mentorship of a senior full-stack engineer who reviewed every PR.

I learned the actual mechanics of software delivery, not just the theory: branching, PR review, iteration, merge and squash workflows. It’s why it belongs here. It means I understand what I’d be managing, from the inside.

In final design polish before productionView the app →
R&D100 AWARD / POPULAR MECHANICS
The patented 3D-printed tamper-evident container with inlaid fiber optics
RECOGNIZED WORK

A 3D-printed tamper-evident container with inlaid fiber optic, designed and developed solo at Los Alamos National Laboratory.

Later recognized with an R&D100 Award and featured in Popular Mechanics, both after I’d moved on to grad school (delayed by patent filing timing, though the work itself was completed during my time there).

Los Alamos · 04/2019–09/2020Read the feature →